Gary Fill Site / Former Sand Mine
Phase II Environmental Site Assessment
Overview
The site is a former 80-acre sand mine, identified as the J-Pit, owned by the City of Gary, and operated by Beemsterboer Slag Corporation as a clean fill site.
Scope
-
Conducted a Phase II Environmental Site Assessment (ESA)
-
Subsurface investigation activities to evaluate the fill included the advancement of six soil borings across the property
-
Used an ATV drill rig to depths of 30 to 34 feet below surface grade
-
Evaluated the types of subsurface fill materials through soil and groundwater sampling
-
Used temporary monitoring wells and analytical testing to confirm or deny the presence of contamination